How to get a Part 145 repair station certificate
The FAA certificates a repair station in five phases. Since 2024 it has added readiness checks, a national queue and deadlines that can end an application. This is the process and the timeline as they ran for us in 2026, with the dates.
The five phases
The FAA’s public guidance describes five phases. Our certification team used different names for three of them and grouped all five into three gates, each with a deadline.
| Phase | FAA guidance calls it | Our team called it | Gate |
|---|---|---|---|
| 1 | Preapplication | Preapplication | Gate I |
| 2 | Formal application | Formal application | Gate II, 135 days |
| 3 | Document compliance | Design assessment | Gate II |
| 4 | Demonstration and inspection | Performance assessment | Gate III, 30 days |
| 5 | Certification | Administrative functions | Gate III |
Before phase 1: the queue
First the shop itself has to meet the regulation: housing, tools, technical data, people and a written system. What part 145 requires, in plain English. You also decide which rating to apply for.
You file a Preapplication Statement of Intent (FAA Form 8400-6) with your local Flight Standards District Office. Under the FAA’s current readiness policy the form is not enough on its own. The office checks your package against a 14-item checklist that includes your manuals, Form 8310-3 and a proposed schedule of events. When it accepts the package, it adds you to the applicant list. Then you wait.
The FAA doesn’t publish a standard wait. Ours was more than a year. Our local office sent status letters with our place in line: 85th in November 2025, 16th in April 2026, called in May.
The useful thing to do with that time is finish the manuals. When the call came we had five days to confirm we would proceed, and about a month before the first meeting. How long each stage took us, day by day.
The readiness notice says an applicant accepted onto the list has already completed phases 1 and 2 and starts at phase 3. Our own file still ran through all five, as described below. Ask your office which path they will hold you to.
Gate I: the preapplication meeting
Ours was held online on June 17, 2026 and lasted six hours, with other applicants on the call. Before it, the FAA asked for a business name acknowledgement with our formation documents, an account request for its document site and an attendance roster. Afterward we signed a form acknowledging the timeline.
Within a week we had a certification project manager, a scoping session to set the application up in the Safety Assurance System, and a certificate number to print on our manuals.
Gate II: formal application and document review
Gate II ran 135 days in two parts.
45 days to file. The formal application is FAA Form 8310-3 plus everything on a document checklist the team tailors to you: manuals, forms, capability list, personnel roster and letters, along with answers to the FAA’s data collection tools. It has to be complete. Ours was accepted for review on July 7.
90 days of review. The team reads every document against the regulations and returns the package with findings. We were told applicants typically get three submissions, and that after a third unsuccessful one the FAA can end the project. Ours was returned on August 13 and September 3. We resubmitted in 11 days each time, and the second revision was accepted.
Gate III: inspection and certificate
Once the documents were accepted, the file went to our local FAA office for the facility inspection. Inspectors came on October 23. They toured the shop, checked tools, calibration and parts segregation, and had us walk a job through our own system from work order to maintenance release. They also reviewed our repairman applications.
Four days later they sent three items to correct. We answered the next day and they accepted the corrections on November 2. The certification team sent draft operations specifications to proofread, and the certificate was issued on November 5, 2026.
Our dates
- The FAA’s certification team tells us we are next
- Preapplication meeting
- Scoping session. Certificate number assigned.
- Formal application accepted
- First return of the document package
- Revision 1 submitted
- Second return
- Revision 2 submitted, then accepted
- Facility inspection
- Inspection findings cleared. Draft operations specifications received.
- Air Agency Certificate issued, 141 days after the preapplication meeting
What has changed recently
- January 2024, reissued January 2026Readiness comes first. Local offices check an applicant against a readiness checklist before adding them to the applicant list. For a repair station it has 14 items, including the manuals and Form 8310-3. A returned package has to be answered within 15 days (Notice 8900.766).
- May 2025, reissued May 2026Stalled applications are withdrawn. An applicant has 15 calendar days to respond to a corrective action notice. Falling behind the agreed schedule, or not having people, equipment or facilities in place when they are needed, can also end the application (Notice 8900.775). Both notices, explained.
- Our experience, 2026A national team may run your file. Ours was handled by the FAA’s Flight Standards Certification Team, with inspectors across the country, online meetings and electronic submissions. Our local office did the facility inspection.
- Our experience, 2026A new sign-in. The FAA’s Safety Assurance System now uses Login.gov, so older accounts may not work.
How long it takes, honestly
There are two waits. The first is the queue, which nobody outside the FAA controls. The second is the certification itself, which ran 141 days for us from the first meeting to the certificate, with two returns along the way.
The second wait is the one a shop can affect, with complete documents and fast answers. That is the work we do.
Cost is a separate question. The FAA charges a U.S. applicant nothing, and the prices for outside help vary more than tenfold. What Part 145 certification costs.
Sources
- FAA: 14 CFR Part 145 Air Agency Certification
- FAA Notice 8900.766, Determine Applicant Readiness for Certification
- FAA Notice 8900.775, Disposition of Incomplete or Insufficient Air Operator and Air Agency Certification Applications (PDF)
- 14 CFR part 145, Repair Stations (eCFR)
The deadlines and dates on this page come from our own 2026 certification and the FAA documents linked above. The FAA can change its process, and your certification team sets your schedule.