How long does Part 145 certification take?
There are two waits: the FAA’s queue, then the certification itself. We finished ours in November 2026, so we can show you where every day went.
The short answer
Ours took more than a year in the FAA’s queue, then 175 days from the FAA’s first notice to the certificate. The FAA publishes no standard time for either wait. Nobody outside the FAA can shorten the first. The second depends on how complete your documents are and how fast you answer.
The first wait: the queue
You get in line by sending your local Flight Standards District Office a Preapplication Statement of Intent (FAA Form 8400-6) with the documents on the FAA’s readiness checklist. When the office accepts the package it adds you to its applicant list, and you wait for inspectors to be free.
The FAA doesn’t publish how long that takes. It depends on how many applicants are ahead of you and how many inspectors the FAA can assign, and both change.
What we can give you is what our own letters said. Our local office wrote to us with our place in line:
- 85th in line
- 16th in line
- The FAA’s certification team tells us we are next
That is 69 places in under five months, then six weeks from 16th to the call. In all we waited more than a year after filing.
A place in line is not a date. The list moves when applicants ahead of you are certificated, withdraw or are dropped for not being ready, and nobody can tell you in advance how many will.
The queue is not dead time
Two things can go wrong while you wait. The FAA can write to you: its readiness notice had offices contact applicants already on the list and gave them 30 days to send the checklist items or be withdrawn. And the call, when it comes, is short notice. We had five days to confirm we would proceed and about a month before the first meeting.
The second wait: the certification
Once the FAA picks up your file, the work runs against a schedule. Our certification team grouped the FAA’s five phases into three gates and gave each a limit.
| Gate | What happens | Limit we were given |
|---|---|---|
| Gate I | Preapplication meeting | A date the FAA sets |
| Gate II | Formal application, then document review | 135 days: 45 to file, 90 of review |
| Gate III | Facility inspection and close-out | About 30 days |
Add the limits together and the outside figure after the meeting was about 165 days. We used 141.
The FAA notice now in force describes a shorter path, in which an applicant who has passed the readiness check starts at document review. Our own file still ran with a meeting and a 45-day filing window. Ask your office which one they will hold you to.
Where our 175 days went
| Stage | Dates | Days |
|---|---|---|
| First notice to preapplication meeting | May 14 to June 17 | 34 |
| Meeting to formal application accepted | June 17 to July 7 | 20 |
| Document review, with two returns | July 7 to September 28 | 83 |
| Review closed to facility inspection | September 28 to October 23 | 25 |
| Inspection to certificate | October 23 to November 5 | 13 |
| First notice to certificate | May 14 to November 5 | 175 |
We count the review as closed on September 28, the day our certification project manager asked for the signed application and sent the inspection notes.
Inside the 83 days of document review
This is the stage where a shop’s own speed shows. The dark blocks are the FAA reading. The yellow blocks are us revising.
- 37 days. The FAA’s first read of the whole package, ending in the first return.
- 11 days. Our first revision.
- 10 days. The FAA’s second read, ending in the second return.
- 11 days. Our second revision.
- 14 days. The FAA accepts the documents and closes the review.
Of the 83 days, 22 were ours. That is the part of the calendar a shop controls, and it is why we plan every return as a two-week job.
The last 13 days
The inspectors sent their list of findings four days after the visit. We sent corrections the next day. They accepted them five days later, and the certificate was issued three days after that.
What makes it longer
- Returns. Each one adds an FAA read and your revision. We were told an applicant typically gets three submissions of the whole package.
- A thin first submission. Our team did not accept partial uploads, and the reviewers read every document against the regulations.
- Missed email. Several requests gave us about a week to answer. We missed the first notice ourselves and caught the reminder.
- Asking for more than you can show. Every rating adds documents and review. We dropped one limited rating during review so it would not hold up the other.
- A facility, tools or people that are not in place when the certification reaches the point of needing them.
What can end it
Under FAA Notice 8900.775 a certification team may treat an application as withdrawn when the applicant falls behind the agreed schedule, lets 15 calendar days pass without answering a corrective action letter, or lacks the people, equipment or facility at the point they are needed.
A withdrawn applicant can reapply, but starts again with the preapplication package while the FAA moves to the next shop on its list. How the 15-day deadlines work.
What a shop can do about it
- Write the manuals while you wait. The 45 days we had to file would not have been enough to start from nothing.
- Put one person on the FAA’s email, or name an agent for service to do it.
- File a complete application early. Ours was accepted 20 days into a 45-day window.
- Plan each return as a two-week job. We turned both of ours in 11 days.
- Run a practice job through your own forms before the inspectors ask you to.
- Answer inspection findings as soon as they arrive. We answered ours the next day.
If the FAA called you today
Using the limits our team gave us, a shop called today should allow about a month to the preapplication meeting and up to 165 days after it. That is roughly six and a half months if every limit is used. We took just under six.
Those are one team’s limits from 2026. Yours will be in the schedule of events you agree with your certification team, and the FAA can change its process at any time.
Sources
- FAA: Become a Certificated 14 CFR Part 145 Repair Station
- FAA Notice 8900.766, Determine Applicant Readiness for Certification
- FAA Notice 8900.775, Disposition of Incomplete or Insufficient Air Operator and Air Agency Certification Applications (PDF)
- Our own certification file: status letters, FAA correspondence and submission dates, November 2025 to November 2026
Every date on this page is from our own file. It is one certification, at one office, in one year. Yours will have its own dates.